Kitchen Remodel Steps: What Happens, in Order

The kitchen remodel steps, in order, are: plan and design, make your selections, confirm permits, protect the house and demolish, fix what the walls reveal, rough in plumbing and electrical, close the walls, install flooring and cabinets, set countertops, then finish with backsplash, fixtures, appliances and a final walkthrough. Each step depends on the one before it, so the order matters more than any single decision.

Homeowners often ask us how long each of those steps takes. The honest answer is that every project is different, and any schedule we could print here would be wrong for your kitchen. What we can do is walk you through what actually happens, why it happens in that order, and where the decisions are that keep a project moving. That’s what this guide covers.

We plan every job in our showroom and build it with our own crew, so the sequence below is how we approach kitchen remodeling in Pittsburgh from the first conversation to the last cabinet door adjustment.

Kitchen Remodel Steps at a Glance

Here is the full sequence in one place. The sections below explain what happens inside each step and what you should be deciding while it does.

  1. Planning, measuring and design
  2. Selections: cabinets, counters, tile, fixtures and appliances
  3. Permits and scheduling
  4. Protection and demolition
  5. Repairs to anything hidden behind the old kitchen
  6. Plumbing, electrical and ventilation rough in
  7. Insulation, drywall and paint primer
  8. Flooring
  9. Cabinet installation
  10. Countertop template and install
  11. Backsplash, plumbing fixtures, lighting and appliances
  12. Final punch list and walkthrough

The most common reason a kitchen remodel stalls is a decision that wasn’t made before demolition. If every selection is locked in before the first cabinet comes off the wall, the crew can work straight through the sequence instead of waiting.

Step 1: Planning and Design

Everything starts with a visit. We measure the room, look at how you use it now, and talk through what isn’t working. Maybe the dishwasher blocks the only walkway when it’s open. Maybe there’s nowhere to set groceries down. Those everyday frustrations shape the plan more than any photo on a phone.

From there, the design takes shape: where the sink, range and refrigerator go, how much counter space sits between them, where people will sit, and how the room connects to the rest of the house. If you are still weighing the big layout questions, our guide to the big decisions to make before demo day goes deeper. Many kitchens work well without moving the layout at all, which keeps plumbing and gas lines where they already are.

Step 2: Selections

Selections come next, and they matter because so much of the build waits on them. Cabinets have to be ordered to exact sizes. Countertops can’t be measured until cabinets are set. The tile you pick changes how the backsplash is laid out. Appliances need to be chosen early because their dimensions drive cabinet sizes, electrical work and gas or venting needs.

Cabinets

Door style, finish, interior storage and exact box sizes. This is usually the selection everything else is measured from.

Countertops

Material, edge profile and color. The final template is taken after cabinets are installed, but the choice is made up front.

Tile and flooring

Floor material, backsplash tile and grout color. These affect how the room is prepped and in what order the crew works.

Fixtures and appliances

Sink, faucet, lighting and every appliance. Their specs tell us where outlets, water lines and vents need to be.

You’ll make these choices in our showroom, where you can see door samples, counters and tile side by side instead of guessing from a screen.

Step 3: Permits and Scheduling

Whether a kitchen needs permits depends on the scope and on the municipality. Requirements vary from one local office to the next, so we check with the local office for each job before work begins rather than assuming. Moving plumbing, adding circuits or changing walls are the kinds of changes that usually get a closer look.

This is also when the order of work is set: when materials are expected, when the crew starts demolition, and when each trade follows. A clear schedule is built around confirmed deliveries, not hopeful ones.

Kitchen after demolition with cabinets removed, patched walls and wiring stubs left for the new layout

Demolition is when the project becomes real. Before anything comes down, the crew protects floors, doorways and the rooms around the kitchen, and plans how debris leaves the house.

Then the old cabinets, counters and often the flooring come out. Wiring and plumbing stubs are left in place, capped and marked, so the next steps can tie into them or move them according to the plan.

A kitchen after demolition. The old cabinets are gone, floor protection is down, and wiring stubs are left in the wall for the new layout.

Step 4: Fixing What the Walls Reveal

Opening walls in an older Pittsburgh house almost always teaches us something. We might find an old patch in the subfloor, wiring that needs to be replaced, a drain that slopes the wrong way, or framing that isn’t square. None of that is visible during the first visit, and it’s the reason no honest remodeler can promise a fixed schedule before demolition.

This step is about correcting those problems before anything new goes over them. It’s also where a good contractor calls you, explains what was found, and talks through options.

Step 5: Rough In Plumbing, Electrical and Ventilation

With the room open, the systems go in. Plumbing lines are run or adjusted for the sink, dishwasher, refrigerator water line and any pot filler. Electrical work adds the circuits and outlets a modern kitchen needs, plus wiring for recessed, pendant and under cabinet lights. Ductwork for the range hood is planned and run now, while it’s still easy to reach.

Lighting deserves its own planning conversation before this step, because once the drywall is up, moving a fixture means cutting into finished walls. Our guide to planning lighting for a kitchen remodel walks through layers of light and where each one goes.

Step 6: Insulation, Drywall and Prep

Once the rough work is in place and any required inspections are done, exterior walls are insulated where needed and the room is closed up with drywall. Seams are taped and finished, and walls are primed. It’s a quieter step, but it sets up everything that follows: straight, flat walls make cabinets and tile go in cleanly.

Patterned porcelain floor tile being laid with spacers in a kitchen

Flooring often goes in before cabinets so it runs wall to wall under them. That makes future changes easier and avoids awkward cuts around cabinet bases.

Some materials and layouts call for a different order, and that’s a decision we make with you during design. Tile needs a flat, solid base, so subfloor prep happens here too.

Patterned floor tile going down with spacers before the cabinets arrive.

Step 7: Flooring

Floor choices affect this step more than people expect. Tile, luxury vinyl plank and hardwood each have their own prep and their own place in the sequence. Once the floor is in, it’s protected again before the cabinets are carried in.

Espresso shaker kitchen cabinets installed in a U shape before countertops

Cabinets are where the new kitchen finally looks like a kitchen. Base cabinets are set and leveled first, then wall cabinets are hung and aligned to them.

Getting this step right is what makes counters sit flat and doors line up. Fillers, panels and trim are fitted so the run looks built in rather than assembled.

A U shaped run of espresso shaker cabinets installed and leveled, waiting for countertops.

Step 8: Cabinet Installation

During installation, the crew also cuts openings for plumbing and electrical, sets the sink base, and confirms appliance openings against the actual appliances. This is the moment to check that drawers clear handles on the range and that the refrigerator door can open fully. It’s much easier to adjust now than later.

Step 9: Countertops

With cabinets set and level, the countertop fabricator takes an exact template. Stone and quartz counters are cut to that template, including sink and cooktop openings, and then installed. Laminate and butcher block follow a similar measure and fit process. Until the final counters arrive, the cabinets stay protected.

White subway tile backsplash being set above espresso base cabinets with the counters covered in protective paper

Finishing work happens in a deliberate order. The backsplash goes on after the counters, so the tile sits right on the finished surface.

Counters stay covered while tile is set and grouted. Then the sink, faucet, disposal and light fixtures are connected, and appliances are set in place.

Subway tile going up between the base and wall cabinets. The countertops are covered with protective paper while the crew works.

Step 10: Backsplash, Fixtures, Lighting and Appliances

This is the step where the room comes together. Tile is set and grouted, under cabinet lights are connected, outlets get their covers, the sink and faucet are hooked up, and appliances are delivered and installed. Cabinet hardware goes on near the end so it isn’t scratched during the rest of the work.

Step 11: Punch List and Final Walkthrough

Finished kitchen with gray shaker cabinets, granite counters, a stainless sink and a refrigerator

Before we call a kitchen finished, we walk it with you. Doors and drawers are adjusted so gaps are even, and caulk lines are checked.

Every appliance is run, every light is tested, and any small item that isn’t right goes on a punch list until it is. Then the room is cleaned so you can start using it.

A finished kitchen with gray shaker cabinets, granite counters and the sink run complete.

Living Through the Kitchen Remodel Steps

Most families stay home during a kitchen remodel. A temporary setup with a microwave, a coffee maker and a folding table in another room helps more than you’d think. Plan where you’ll wash dishes, and keep a path clear for the crew. Our guide to living in your home during a renovation has a full checklist.

Mistakes That Throw the Sequence Off

  • Changing a cabinet size or appliance after the order is placed.
  • Choosing tile or counters after demolition has started.
  • Buying appliances without checking their exact dimensions against the plan.
  • Adding lighting or outlets after drywall is finished.
  • Skipping a walkthrough of the plan before work begins.

Frequently Asked Questions

What is the first step in a kitchen remodel?

Planning and design. Before anything is ordered or removed, the room is measured, the layout is set, and the way you use your kitchen is worked into the plan. Selections follow right after.

How long does each kitchen remodel step take?

Every project is different. The size of the kitchen, the condition behind the walls, material deliveries and any layout changes all affect the schedule, so we give you a plan for your specific kitchen rather than a general number.

Do cabinets or flooring go in first?

In many kitchens the floor goes in first so it runs under the cabinets. Some materials and layouts call for a different order, and we decide that with you during design.

When are countertops measured?

After the base cabinets are installed and leveled. The fabricator templates the actual cabinets so the counters fit exactly.

Can we use the kitchen during the remodel?

Usually not once demolition starts. Most families set up a small temporary kitchen in another room until the sink, counters and appliances are back in place.