The right bathroom remodel order is plan, demolish, rough in the plumbing and electrical, close the walls and waterproof, set the tub or shower base, tile, then install the vanity, toilet, fixtures and trim. Each step depends on the one before it, so getting the sequence right is what keeps you from tearing out new work to fix something that should have been handled earlier.
Below is the order we follow on every bathroom we build, and why each step sits where it does. It’s the same sequence behind every job in our bathroom remodeling in Pittsburgh, from a small hall bath to a full primary bathroom. Every project is different, and older homes like to add surprises, but the order itself rarely changes.
Why Bathroom Remodel Order Matters
A bathroom puts plumbing, electrical, ventilation, waterproofing, tile and cabinetry into one small room. When the steps happen out of order, the mistakes are expensive to undo. A vanity set before the floor sits too low. Finish paint goes on before tile and gets scraped. A plumber has to cut into finished drywall because a valve was set at the wrong height.
Following the sequence protects the work you’re paying for. It also makes the project easier to live through, because each trade arrives to a room that is ready for them.
Step 1: Plan the Layout and Choose Materials
Planning is the step that prevents most problems later. Decide if you’re refreshing the room or taking it down to the studs. Settle the layout, especially whether the toilet, shower or vanity will move. Moving plumbing changes everything that follows, so it has to be decided first. If money is tight, our guide on how to renovate a bathroom on a budget shows where to spend and where to save.
Then choose your fixtures, tile, vanity and lighting before demolition starts. We design every bathroom with homeowners in our showroom, so the selections are made and ordered before anyone picks up a pry bar. If you’re still deciding between a tub and a shower, our guide on walk-in shower vs. tub can help you choose. This is also when we check with the local office about what the job needs, since requirements vary by municipality.
Step 2: Demolition
With selections made, the room comes apart. Water and power to the room are shut off, then the toilet, vanity, mirror, tub or shower, wall finishes and flooring come out. The goal is to reach the framing and subfloor without damaging the rest of the house.
Expect surprises here. Hidden water damage, soft subfloor and old wiring often show up once the walls are open, especially in older Pittsburgh homes. Fix them now, while everything is exposed. It is far harder once the new tile is on the wall.
Our post with before and after photos of a shower renovation shows this open wall stage next to the finished tile.
Steps 3 to 5: The Work Inside the Walls
These three steps happen before anything you will see in the finished room, and they decide how well it holds up.
Rough in plumbing and electrical
New supply and drain lines are run for the shower, tub, sink and toilet. Outlets, lighting and the vent fan wiring go in. This is also the time to add blocking in the walls for grab bars, towel bars or a wall hung vanity.
Close the walls
Cement board or a foam board system goes in the wet areas, and moisture resistant drywall covers the rest. Insulation goes into exterior walls before they close.
Waterproof the wet areas
A waterproofing membrane goes over the shower walls and floor. This layer is what keeps water out of the framing, so it is never the place to cut corners.
Step 6: Set the Tub or Shower Base
The tub or shower pan goes in before any tile, set level, fully supported and connected to the drain. Then it gets tested. Running water through it now, while the drain is still easy to reach, is the cheapest leak check you will ever do.
Step 7: Tile the Walls and Floor

Tile follows a set sequence: shower walls and surround first, then the floor. The wall tile sits on top of the tub or pan flange so water sheds into the tub instead of behind it. The floor goes in after, working from the back of the room toward the door.
Once the tile is set, it is grouted and, depending on the grout, sealed. Then the room is ready for the pieces you will touch every day.
White tile on the shower walls and ceiling, with a window set into the tiled wall.
Some people prime and paint before tile so drips land on surfaces that will be covered anyway, and then finish paint at the end. Either way, the final coat comes after the fixtures are in.
Step 8: Install the Vanity, Toilet and Fixtures

Now the room starts to look like a bathroom. The vanity and top go in, the sink and faucet are connected, and the toilet is set on the new floor. The shower valve trim and showerhead are installed over the finished tile, and any shower door goes on.
Setting fixtures last protects them. A new faucet or showerhead that goes in before tile tends to get scratched, splashed with thinset or knocked out of place.
A chrome showerhead and shower valve trim installed on white wall tile.
Step 9: Lighting, Trim, Paint and Final Caulk

The last step pulls everything together. Light fixtures, outlet covers and the fan grille go on. Baseboard, door casing, towel bars and the toilet paper holder are installed. Walls get their final coat of paint.
Caulk goes in last, at the tub and tile joint, around the toilet base and along the back of the vanity. Then the room is cleaned and walked through together, so you can see every finished detail.
A nearly finished bathroom with a tub and acrylic shower surround, toilet, vanity and towel bars, before the last outlet cover goes on.
What Happens When the Order Gets Skipped
Vanity before the floor
The cabinet ends up sitting low or the floor has to be cut around it, which leaves a gap that is hard to finish cleanly.
Tile before the plumbing test
A slow drain leak shows up after the wall is tiled, and the only way in is through the new tile.
Fixtures before paint and tile
Finishes get scratched, splashed or removed and reinstalled, which adds work for no benefit.
No blocking in the walls
Grab bars, heavy mirrors and towel bars have nothing solid to anchor into once the walls are closed.
This is a big reason we build every bathroom with our own crew. The same people carry the job from demolition to caulk, so nothing gets skipped between trades. For more on why that matters, read our post on hiring one bathroom remodel contractor instead of managing separate subs.
Frequently Asked Questions
What is the first step in a bathroom remodel?
Planning. The layout, fixtures and materials should be decided before demolition, especially anything that moves plumbing, because that choice affects every step after it.
Do you tile the floor or the walls first in a bathroom?
In a shower or tub surround, walls usually come first so the wall tile laps over the tub or pan flange. The main floor usually follows, working toward the door.
Does the vanity go in before or after the flooring?
In most bathrooms the floor goes in first and the vanity sits on top of it. That keeps the vanity at the right height and gives a clean finish at the base.
When should you paint during a bathroom remodel?
Many crews prime and paint early, before tile and fixtures, then apply the final coat near the end. The finish coat always comes after the messy work is done.
How long does a bathroom remodel take?
Every project is different. The scope, the condition behind the walls and material selections all change the schedule, so we talk through it for your specific bathroom during the consultation.